If 12 men and 16 boys can do a piece of work in 5 days and,13 men and 24 boys can do it in 4 days, how long will 7 men and 10 boys take to do it,
Answer Posted / sapan anand
12m + 16b = 1 /5 days
13m + 24b = 1/4 days
5( 12m +16b) = 4( 13m + 24b)
1m = 2b
12m + 16b = 5 days
12m + 8m = 5 days
20m = 5 days
7m + 10b = 7m + 5m = 12m
1m = 5 x 20
12m = 5 x 20 / 12 = 8 1/3 days
| Is This Answer Correct ? | 11 Yes | 5 No |
Post New Answer View All Answers
If the total distance of a journey is 120 km .If one goes by 60 kmph and comes back at 40kmph what is the average speed during the journey?
A person has his own coach&whenever he goes to railway station he takes his coach.One day he was supposed to reach the railway station at 5 O'clock.But he finished his work early and reached at 3 O'clock. Then he rung up his residence and asked to send the coach immediately. He came to know that the coach has left just now to the railway station.He thought that the coach has left just now to the railway station.He thought that he should not waste his time and started moving towards his residence at the speed of 3min/hr.On the way,he gets the coach and reaches home at 6 o'clock.How far is his residence from railway station.
What are all the java technical questions?
in 8*8 chess board what is the total number of squares refer odel
find 70.56/ 11.2 =?
I HAVE APPEARED FOR ALLAHABAD BANK ON 21-02-10, I WANT TO KNOW THE SECTIONAL CUT OFF'S FOR CATEGORY.
Find the next series: AA AB BC CE ?
A work is done by the people in 24 min. one of them can do this work a lonely in 40 min. how much time required to do the same work for the second person.
In 80 coins one coin is counterfeit what is minimum number of weighings to find out counterfeit coin
f(f(x))=81 THEN VALUE OF X=
In the given figure, PA and PB are tangents to the circle at A and B respectively and the chord BC is parallel to tangent PA. If AC = 6 cm, and length of the tangent AP is 9 cm, then what is the length of the chord BC?
An array was given and we were required to write a function : int CalculateThirdHighest(int a[ ]) : which calculates the third highest number in the array. While coding in C remember to calculate the length of array using formulae length of array=sizeof(a)/sizeof(int). Because the number of elements of array were not passed as argument. i want a solution in C/C++ language
The average of 13 papers is 40. The average of the first 7 papers is 42 and of the last seven papers is 35. Find the marks obtained in the 7th paper?
What is the selling price of a car? If the cost of the car is Rs.60 and a profit of 10% over selling price is earned.
write a program that prompts the user to enter three sides of a triangle and prints whether it is a right triangle or not.