Why attemperation is required in HRSG in a combined cycle
power plant?

Answer Posted / sunil

In CCPP secondary superheater coils are located near to flue gases and exhaust of gas turbine enters boiler . Exhaust of GT are at high temp around 600C

Is This Answer Correct ?    0 Yes 1 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

Looking for Bently Nevada surplus 3300/52-01-00-00 Reverse Rotation Monitor , 4 pieces.

3085


what is the basic use of power plant in equipment

1312


We have Demin Closed cooling water system with expansion tank for cooling oil system. Expansion tank having N2 bladder. Whenever N2 bladder bursts out, Closed cooling water circuit pressure drops and make-up happening, eventhough there is no leaks. And how Circuit pressure drops?

1530


By any way can we increase the B check hours from 300 to 500

1797


How We Calibrate the vaccum transmitter?

1559






how to differentiate between "ALL fuel lost" and "All Fuel Lost" in Boiler MFT condition?

1332


some one can tell me how residual type excitation is provided through transformers to an AC generator without any battery or PMG&excitor

2057


im try to calculating seawater flow required for SW-FGD system. I need a guide, equation or method to do it, can some one help me! Thanks very much

1591


DCS marshaling Cabinet Power supply can be replace during plant running time? Answer Yes it is possible. I am talking about the controller and cards power supply modules. They are always redundant and connected through diode so that if one power supply fails the other can take the charge immediately.so it is possible to replace one of them in running plant if the other one is healthy. MY question is how switching done.

618


what is natural frequency of turbine shaft .

1837


LAPT working in alternator / generator

2871


Which will have more strain energy 1.Spring 2.Circular disc 3.Solid square plate.

1964


why is the in steam turbine axial displacement of active side thrust pad is positive and non active side thrust pad is negative.

2871


procedure of how to generate power in solar plant.

1467


can u please tell me how to calculate the concrete quantity for a under reamed pile? r=300mm,depth=3m for a cylinder and for bulb l=.750mm,width=.525

1380