Why attemperation is required in HRSG in a combined cycle
power plant?
Answer Posted / sunil
In CCPP secondary superheater coils are located near to flue gases and exhaust of gas turbine enters boiler . Exhaust of GT are at high temp around 600C
Is This Answer Correct ? | 0 Yes | 1 No |
Post New Answer View All Answers
what is the meaning of SST300 V56A in SIEMENS turbine
Looking for Bently Nevada surplus 3300/52-01-00-00 Reverse Rotation Monitor , 4 pieces.
What is LB-SR.
How do you consider that you can improve and what assistance do you need to achieve this
explain how the third harmonic content of the magnetising current affects transformer design
why is the in steam turbine axial displacement of active side thrust pad is positive and non active side thrust pad is negative.
what's the moog valve
operation
How to calculate power press toneage
what is natural frequency of turbine shaft .
Qatar Fertiliser Company (QAFCO) Shortlisted me for interview (got the intel from my source) for Field Operator- Utilities post. Please let me know what kind of questions they asked? ... this position requires 5 years of experience in Power Plant and background Diploma in Electrical/ Mech. ... my Background is Electrical and I am a sub Assistant Engineer (Operation) at a private HFO based Power plant... PS: Please Let me know what preparation should I take to obtain the Interview which will be take place In Bangladesh soon
procedure of how to generate power in solar plant.
How to calculate boiler capacity? I have 1 Autoclave, Which has to use for AAC block. Dimension for this Autoclave is - 13 Meter Length & 2.2 Meter Diameter.
what does mean by kva rating
what is the basic use of power plant in equipment