Why attemperation is required in HRSG in a combined cycle
power plant?

Answer Posted / sunil

In CCPP secondary superheater coils are located near to flue gases and exhaust of gas turbine enters boiler . Exhaust of GT are at high temp around 600C

Is This Answer Correct ?    0 Yes 1 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

what is the meaning of SST300 V56A in SIEMENS turbine

3874


Looking for Bently Nevada surplus 3300/52-01-00-00 Reverse Rotation Monitor , 4 pieces.

2965


What is LB-SR.

2477


How do you consider that you can improve and what assistance do you need to achieve this

1325


explain how the third harmonic content of the magnetising current affects transformer design

2762






why is the in steam turbine axial displacement of active side thrust pad is positive and non active side thrust pad is negative.

2751


what's the moog valve

1039


operation

1361


How to calculate power press toneage

1538


what is natural frequency of turbine shaft .

1708


Qatar Fertiliser Company (QAFCO) Shortlisted me for interview (got the intel from my source) for Field Operator- Utilities post. Please let me know what kind of questions they asked? ... this position requires 5 years of experience in Power Plant and background Diploma in Electrical/ Mech. ... my Background is Electrical and I am a sub Assistant Engineer (Operation) at a private HFO based Power plant... PS: Please Let me know what preparation should I take to obtain the Interview which will be take place In Bangladesh soon

1756


procedure of how to generate power in solar plant.

1369


How to calculate boiler capacity? I have 1 Autoclave, Which has to use for AAC block. Dimension for this Autoclave is - 13 Meter Length & 2.2 Meter Diameter.

1817


what does mean by kva rating

991


what is the basic use of power plant in equipment

1218