Calculate the quantity of concrete for the following.
2 Under-reamed cast in situ pile of 300 mm dia. of 10.00 m
length.

Answer Posted / pravat

Volume=π/4 {Ld^2+0.4N(D^2-d^2)(D-d)}
Where d=dia of pile
D=dia of under ream
L=length of pile
N= no of under ream.
This the formula for pile with any no of under reams.

Is This Answer Correct ?    52 Yes 14 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

As per Kandal suggestions, we have implemented rolling starts on 140 (+/- 5) degrees and we kept 3 rollars to complete the rolling before falling 125 degrees and the Aggregate AIV is below 22. But When the DBM bed is being rolled 3rd high viabration, (Before 1 plain & low ,2 high Viabrations), the aggregate is getting sharp edge agg. projections are damaged. As the literature is said that, the VG-30 Grade having better control the temp. susceptibility than Penetration grade. if so we could not get this problem at site. But we are facing on site. let me know.

1497


rate analysis for cement pointing 1:4 , for 100 sq m

3706


Design an underground tank of internal dimensions 6m x 3m x 3m. The soil surrounding the tank always remains dry. The tank shall be provided with a roof slab. The soil weighs 16000 N/m3 having an angle of repose of 30.

1634


I want to know the material required per square foot in rcc roof. i.e. steel: kg/foot, cement/foot etc.

1526


howto calculate the quantities of material used in fly ash brick after finding the volume??

1184






Define What is the tallest man made structure in the world?

660


how to decide the mortar ratio 1:4,1:6 in masonry? same in plaster 1:3 and 1:4? which code or any document reference taken to define proportion?

1654


Use of coping on terrace wall and in 4" wall is compulsory or not ?

1104


Caching, Multithreading and RAMBUS are 3 methods for resolving the Bottleneck problem. Please give an explanation for each one (how are they resolve the problem?)

1816


How many cum of 9.5mm stone in 1 ton ?

2110


Explain the various stages of the project planning process in construction?

710


what is stressing

5821


WHAT IS THE % OF CONCRETE WASTAGES PERMITED IN A LARGE PROJECT ? AND WHICH IS CODE TO BE REFERED.

1585


Form where IS456 is adopted in 1978?

1504


Explain different types of rcc pipes.

711