We are working building soling work so soling thickness given 230mm but total are 50 cum. So I am purchased how meny tons is here spreading plz. Tell me
Answer Posted / naresh
its simple bro
1 cum soling material have 1.55 tone weaight so 50x1.55=77.5 tone
| Is This Answer Correct ? | 1 Yes | 0 No |
Post New Answer View All Answers
how to remove the quantity of metal 1 and metal 2 in concrete
Name the main components of a cad gui?
What does civil status mean?
CAN V USE CRUSH SAND FOR CLAY BRICK MASONARY
cement, sand, aggregate,reinforcement & concrete consumption per square feet in multi storeyed building
how much cement is consumed by a stone masonry wall 17.7m long,0.55m wide and 1m high
What is the use of offset command?
what is mail role & relationship between senior Civil engineer to consultants , Construction manager ,project manager, project engineer ,Technical engineer & qa/qc engineer ? what is the responsibilites of Senior Civil Engineer?
how much tempareture are required to make liquid state of pid leed
What are the govt approvals required for starting of power project. means from initial site grading and excavation work.exm. blasting in hard rock, deep excavation, cut off trees from site.
1. What is coefficient use for calculation of shuttering. 2. What is coefficient use for calculation of reinforcement in one cum of concrete.
in 100 cft = 1350 bricks in 100 cft = ? bloks
what is spacing of wallar support of 3m column. the thickness of column is 0.25 m.
I need model question papers for writing the Dubai municipality exam,for G+1
How much sand and cement requirement for 1 SQM 125mm thickness Brickwork