Trapezoidal footing length = 2m , B=1.7m D=0.5m and d-
0.15m. Can anybody help and calculate quantity of concrete
by explaining all formulas involved.
Answer Posted / umesh gumme
avg of D & d=0.5+0.15/2=0.325
size of footing 1.7*2 no of footing assume 5
no*(avg+D)*(avg+D)*(D-d)
5*(0.325+0.5)*(0.325+0.5)*(0.5-0.15)
5*0.825*0.825*0.485=1.65 m cube
| Is This Answer Correct ? | 0 Yes | 1 No |
Post New Answer View All Answers
What are the different types of runners?
a sewer which receives the discharge of no. of house sewer is called house sewer lateral sewer intrcepting sewer sub-main sewer
what is the difference between natural draught cooling tower and induced draught cooling tower
what is meant by csr in foundation? what is sbc?what is meant by contour line?
How much river sand contain the 6 & 10 wheeler truck? Or Maximum sand that any type of truck carry?
What will be weight of 0.5mm GI sheet per sq.ft?
manhole chamber having height of 2300 mm and thickness of brickwork is 230 mm and dia of opening covering is 560 mm and bottom length vertical is 1500 mm (1:4) brick masonry and plaster 12 mm on both sides..how to estimate the no bricks used with mortar cement bags and sand for total chamber including plaster.
VAT and CST ? Which benefits for buyer ? Why benefits?
How to calculate dry of volume of concrete constant?How it comes 1.54 or 1.57
give me the mix proportion for design mix concrete M 7.5 grade 1:4:8
60-70 grade of Bitumen is VG-30 ?
Does brick grows bigger every year?
Define What happens to Load at yielding ?
What is limit state method and working stress method and ultimate method
what is SDLC ?and write a 'c'program for to swapping the three numbers?