Answer Posted / hariskumaar
The first process in MRP is the checking of the planning file entry.
The planning run and the scope of the planning run (which materials are planned in which planning run) are controlled by the planning file.
The planning file contains a list of all materials relevant to the planning run. As soon as a material master record is created with MRP data and a valid MRP type, this material is then automatically included in the planning file.
During MRP run at plant level system checks for the materials which are having indicator activated in planning file and plans those materials and will not plan the materials for which this indicator is not activated….this reduces the run time of the MRP..
| Is This Answer Correct ? | 1 Yes | 0 No |
Post New Answer View All Answers
What is routing in sap pp?
What are sequence, parallel, overlapping, splitting and where can we assign these
What is the Difference between TECO and CLSD?
If there are some errors in goods movements, and less stock of material consumed, how can we solve that problem in sap ?
Mention what are the types of master views for production and planning?
What is MTS and MTO and the difference between them?
What is sap pp?
How requirements( pir,sles order, customer requirement) are reduced after they are produced?
What is end user training
What is planned consumption and unplanned consumption?
what are the constraints of Variant configuration?
What change management functions do you require? How do you want to define the validity of BOMs (based on date/freely definable parameters)? Must existing change histories be transferred to the R/3 System?
What is SOP and types of SOP?
How can you get planned orders scheduled so that you can do capacity leveling ?
What is the data you give in S.O.P screen?