Question 81 - (a) In natural gas pipe sizing, the length of the pipe from the gas source metre to the farthest appliances is 60 feet. The maximum capacities for typical metallic pipes of 60 feet in length are : 66 cubic feet per hour for pipe size of 0.5 inches; 138 cubic feet per hour for pipe size of 0.75 inches; 260 cubic feet per hour for pipe size of 1 inch. By using the longest run method : (i) Find the best pipe size needed for the capacity of 75 cubic feet per hour. (ii) Estimate the suitable range of capacities for the pipe size of 1 inch. (b) The maximum capacities for typical metallic pipes of 50 feet in length are : 73 cubic feet per hour for pipe size of 0.5 inches; 151 cubic feet per hour for pipe size of 0.75 inches; 285 cubic feet per hour for pipe size of 1 inch. By using the branch method find the best pipe size needed for the capacity of 75 cubic feet per hour when the length of the pipe from the gas source metre to the appliance is 52 feet.

Answer Posted / kangchuentat

Answer 81 - (a)(i) Best pipe size needed = 0.75 inches for the capacity of 75 cubic feet per hour. Data for a metallic pipe of 60 feet in length and maximum capacity of 138 cubic feet per hour instead of 66 cubic feet per hour are selected. (ii) Range is more than 138 but less than or equal to 260 cubic feet per hour for pipe size of 1 inch. (b) Best pipe size needed = 0.75 inches for the capacity of 75 cubic feet per hour. Data for a metallic pipe of 60 feet in length instead of 50 feet and maximum capacity of 138 cubic feet per hour instead of 66 cubic feet per hour are selected. The answer is given by Kang Chuen Tat; PO Box 6263, Dandenong, Victoria VIC 3175, Australia; SMS +61405421706; chuentat@hotmail.com; http://kangchuentat.wordpress.com.

Is This Answer Correct ?    0 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

Explain how can you estimate the efficiency of a pump?

598


How can you prevent bridging in a dilute phase pneumatic conveying system?

633


Is there any way to slow coke formation in ethylene furnaces?

739


Explain what are the criteria involved in choosing mass balances for components?

580


When should one be concerned with the tube wall temperature on the cooling waterside of a shell and tube exchanger?

609






Why do we apply on iron articles?

657


What is a good method of analyzing powders for composition?

672


What is the largest application for surfactants?

676


Are there any alternatives to scraping a shell and tube if a capacity increase will make the pressure drop across the exchanger too large?

686


What is the purpose of capacitor?

1374


Can any one send me the sample test papers of IOCL entry exam to be held on 6th july 2008. Also plz send the interview questions that cud probably be asked........i wud be highly obliged if u can send a few test paers and other stuff @ inderjeetd@gmail.com.........Inderpreet

2217


What does capacitor load means? How does it connect?

586


have any one question paper of institute of plasma research center for aptitute as well as technical?

6489


what are the chemicals used in PFR and MFR to Process?

2723


I will complete chemical engg next yr from a deemed university. Earlier I dropped 2 yrs after std 12th. Then I got 2 yr back while completing engg, due to reasons beyond my control. Will I face any problem while applying for job. More so not many core companies come to our collg for placement. So i want to know which all companies can I apply to get a job?

1740