Answer Posted / mohamed alfaiz
actual volume brick ------- 19cm x 9cm x 9cm = 0.0015m3 (1m3/0.0015)=666.66 nos
thickness of mortar -------- 10mm
volume of brick + mortar------- 20cm x10cm x 10cm =0.002m3 (1m3/0.002)=500 nos
=(1m3 -500/666.6)
=0.25m3 of mortar
quantity of cement required
unit wt of cement 1440kg /m3
ratio 1:5
=1440/5
=288kg/m3 x 0.25m3
72kg/50kg per bag
=1.44bag of cement
sand
0.25m3
9cft
| Is This Answer Correct ? | 10 Yes | 1 No |
Post New Answer View All Answers
what is the criteria for the finalisation of pavement thickness in road project?
How to use of me trial wall plaster 6mm , 10mm par sqm. use in sand and cement ?
is it fair to recruit another prestressing agency once earlier agency has provided guide cone for post stressing the Concrete -I girders? It is observed that the bearing plate of another agency is not matching with the earlier one resulting in protruded strands after stressing from the face of girder. Kindly advice.
What is the material consumption- cement,sand,tiles etc for Toilet dado?
What is the method of soil replacement test?
Explain what is Critical Path Method (C.P.M)?
01. a. Diagram of a slump cone…………… 1 b. Size of Slump Cone…………… 1 c. Volume of a slump cone by av. Dia method…………… 1 d. Volume of a slump cone by av. area method…………… 1 e. Volume of a slump cone by frustrum method …………… 1 f. Angles of slump cone …………… 1 g. Slump measured by slump cone due to…………… 1 h. Slump does not measured by cylinder / cube due to …………… 1 i) ii) i. Slump cone is to be filled in……………………..Layers.
Trapezoidal section footing calculation of Volume & its Area
what is the use of steel rods of 16mm or 20mm used for 4.45mts for closing gutter.one mate consumes how many kgs with a gap of 6inches.
reinforcement slab, beam and column formulas?
How to do rate analysis for concrete work including shuttering work?
I want some common questions which have been asked in interviews of NTPC Limited,Satluj Jal Vidyut Nigam Ltd.,and Bharat Heavy Electricals Ltd.
how much shouid be the rate for ready mix concrete per cubic meter
As per Kandal suggestions, we have implemented rolling starts on 140 (+/- 5) degrees and we kept 3 rollars to complete the rolling before falling 125 degrees and the Aggregate AIV is below 22. But When the DBM bed is being rolled 3rd high viabration, (Before 1 plain & low ,2 high Viabrations), the aggregate is getting sharp edge agg. projections are damaged. As the literature is said that, the VG-30 Grade having better control the temp. susceptibility than Penetration grade. if so we could not get this problem at site. But we are facing on site. let me know.
trapozidal