Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

How to calculate water tank capacity in Ltr

Answer Posted / senthil473

In 1 m3 of volume we can accommodate 1000 kg ie.1000 liter of water. so that first find the volume of the container in m3 and multiply that with 1000, you can get the quantity of water
in liters.
ex. if the volume of the container is 3 m3, the water can be stored is = 3*1000=3000 liter.

Is This Answer Correct ?    0 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

How can you produce desired alloys and discuss their applications in daily life.

1223


What are the different methods for drawing an arc?

1245


what is w/c ratio in dry lean concrete for m10 mix design

8457


Does brick grows bigger every year?

1143


what is flashing?

1171


minimum number of bars in a beam? minimum and maximum column size and beam size ? minimum and maximum aggregate size used in multistorey residential building for columns,beams,slabs?

5436


what is the Asfalt test?in road constraction..?

2102


it is possiblee to produce concrete with out cracks...

1908


What is the difference between routing maintenance and major maintenance in school facilities?

1117


what is the basic difference between Coloumn & Shear Wall

2212


what is the price of a cubic meter of concrete on international market?

1221


why we use 19x9x9and 20x10x10 but not other

2161


Design a cantilever slab to carry a live load of 2000 N/m2. The overhang of the slab is 1.20m. b) A slab over a room is 4.75m x 4.75m. The edges of the slab are simply supported and the corners are not held down. The live load an the slab is 300 Kg/m2. The slab has a bearing of 15cm. On the supporting walls. Design the slab as per Rankine - Grashoff theory. Assume weight of R.C.C. = 2400 Kg/m2.

2860


the water is flowing through a velocity of 1.5m/s in a pipe of length 2500m and dia 500mm. at the end of pipe a valve is provided. find rise in pressure 1. if the valve is closed in 5 seconds. 2. if the valve is closed instantaneously. take value of c = 1460m/s, pipe to be rigid and bulk modulus of water - 19.692x10' n/sqcm

2359


Please tell me Detail cost of providing& laying nominal mix design 1:2.5:5,40mm nominal size.curing complete e/c cost of form work in foundation and plinth i/c carriage.

2246