How to calculate the amount of Brick,cement & sand required
for 1 cum of 230mm thick brick work with ratio 1:5 please
give me an answer with detailed step
Answer Posted / sheraz
No of Bricks= volume of total brickwork / volume of brick= 1 / 0.002 =500 NO.s
Volume of mortar is 30% of volume of brickwork = 0.30 cum
dry volume of mortar = 0.30 x 1.54 = 0.462 cum
So cement Quantity = 1x0.462/1+5 = 0.077 cum
divide it by the volume of cement bag that is 0.0347 = 0.077 / 0.0347 = 2.22 bags
sand quantity = 5 x 0.462 / 1+5 = 0.385 cu m
Is This Answer Correct ? | 0 Yes | 2 No |
Post New Answer View All Answers
how much concrete solid/hollow block are manufacture per 50 kg cement bag in differnent sizes like 400x200x200mm, 400x200x150mm, 400x200x100mm. And need proper ratio as per sale quantity. pls send my mail mathi7599@gmail.com searching last two years not yet get pls find and enclosed pls. need practical analysis.
how do you calaculate the total steel quantity of an rcc building using thumb rule?
Explain what are the phases inspections are done by local authority while construction?
what is shuttering co efficient?
where can i get the previous question papers for rrb section enginerr (civil)
how to calculate the scour depth
difference between fc and fc'?
what is the use of water bar in water tank and is this an extra item in estimate?
Explain the mechanism of cavitations in pipes and drains?
What is the maximum crushing load in Kg & crushing strength in N/mm2 for M25 & M 15 Grade concrete
What are the basic use of runners and standards of pipelines?
What is modular elasticity?
what is flashing?
Why do you want to work here
What are the disadvantages while using stone dust as filler in pavements?