If process order is technically closed, by mistake
I want to process that order again can I do it?

Answer Posted / arun k

If order is in teco status , then this order is irrelevant to mrp , all purchase requisation and planned order is cancelled for that order and capacity also cancelled for that order, first you need to do the revoke teco and process it

Is This Answer Correct ?    0 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

How can you get planned orders scheduled so that you can do capacity leveling ?

726


How to insert an inspection checkpoint at the end of an operation?

840


Explain service level agreements

695


How did you configure the payscale structure?

676


Tell some standard order types and what configure done for current project

1654






What is meant by payscale structure?

645


What is Planning time Fence?

1084


What is alternate item group?

1077


Do you have any idea about Capacity Planning?

1587


What is mrp group and what is the use of it?

699


What is Individual and collective requirements and differecne between them in MTO scenario?

1691


What are the types of MIC?

1308


How system calculate the actual cost?

1373


Mention how mrp (material requirement planning) types are classified?

782


What are the levels of batch, explain batch determination process?

1183