How to Calculate the spacing of bars if we use 12 mm dia. bars instead of 10 mm dia. bars. Whereas the 10 mm dia. bars spacing given 0.250 as pr drawing. ?
Answer Posted / sumit007.1991
d1^2/S1 = d2^2/S2
10x10/0.25 = 12x12/s2
=> s2 = 0.36
| Is This Answer Correct ? | 1 Yes | 0 No |
Post New Answer View All Answers
may i know the detailed description of cutting length
how to convert sand in Cft to Kgs
how can we calculate steel value, depending on load
115mm thickness brick work how to required mortar
why should we use 20mm graded metal only in vrcc?why we shouldnot use 40mm metal?
how to frame the sentence in voucher pad ? Description : 1.Food Expenses during site visit 2.Stamp Paper approval expenses 3.Travelling expenses 4. sweet distribution
Which ratio use for cement selery???
I am a civil engineering student and going to attend interview in this week in an IT company.Will they ask me questions about my area of interest or cs
Which tests are performed on soil to decide the type of foundation to be provided.
How is calculate the cube molt
for 32 dia (EQR HYSD steel) bar how much deduction for 45 and 90 degree band
) Design a gussetted base for a column section consisting of one sc 250 with two cover plates 300 x 25 mm carrying an axial load of 2500 KN. The S.B.C. of soil is 250 KN/m2 and the permissible bearing pressure on concrete is 4000 KN.
for 16mm thick cement plastring 1:6 on 100 Sq.m.New brick work,the quantity of cement required is.
what values & beliefs have guided you in your career path
how many shuttering material required for 1000 sq.m built up area.