How to calculate 45 degrees bend Steel bar length in Slab
Reinforce ment
Answer Posted / mehul kothari
For each bent up of 45°
Add 0.42*(d - 2*cover)
Where d is (depth of slab)
And 2*cover = top cover + bottom cover
| Is This Answer Correct ? | 9 Yes | 5 No |
Post New Answer View All Answers
suppose that 156000 sq.ft rcc work builtup are.how many % of brick work to rcc work.
What are the ingredients of pre-stressed concrete?
HOW MANY BAGS OF CEMEMT USED IN PER M2 OF PARTITION WALL
i) Distinguish between Theodolite and dumpy Level? (Marks-8) ii)Distinguish between Viscous and Turbulent flow? (Marks-8) iii) Distinguish between nominal and design mix? iv) What is standard sand? v) Explain the term plane stress? Vi) Differentiate between principal plane and principal axis? Vii) write short notes on Elastic limit of structural steel? viii) Write short notes on stress concentration? ix) write short notes on "Grading of Sand" ? x) How many grades of concrete are there under standard concrete?
What is the primary difference between adsorption and absorption?
Caching, Multithreading and RAMBUS are 3 methods for resolving the Bottleneck problem. Please give an explanation for each one (how are they resolve the problem?)
how will calculate 4"thick solid block quantities 1m3 sand cement ratio and breack up detail
Explain moment of inertia and its importance.
What Is the Thumb rule to calculate depth and dia of pile required to carry specified load on differeent soil
if i used salt as a add mixture in concrete, then what will happen and what are the naturally available add mixtures.
1:4:8 pcc calculation 591 cu.ft
What is the use of extend command?
how to find quantity of concrete in PCC M15
What is the difference between EPC,DBOOT and BOOT.
How to arrive d*d/162 , for finding the kg per meter , wt of steel