how to carry out rate analysis for RCC work in column using M20 ?

Answer Posted / rajasekar

cost of M20 concrete and concrete mixing labour.The labour part may change from place to place.If it is hand mix, we have to consider the lead and lift of material.Shuttering and steel not to consider in the concrete volume.

Is This Answer Correct ?    2 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

Thumb rule for steel qty for 1m2 in kg/m2 column slab footing beam

5141


what is the cost differene of a same structure when it is constructed with brick masonary, and when it is constructed with concrete as a frame structure.????????

1486


Explain what are the phases inspections are done by local authority while construction?

754


how pumping of concrete effects the quantity of material used in it?

1301


150mm bricks size how many use 4.14 m3

1421






What is diversion tunnel in a dam?

698


The concrete slump recommended for beams and slabs; is?

773


Who built the sears tower?

649


What is passive earth pressure ?

734


manhole chamber having height of 2300 mm and thickness of brickwork is 230 mm and dia of opening covering is 560 mm and bottom length vertical is 1500 mm (1:4) brick masonry and plaster 12 mm on both sides..how to estimate the no bricks used with mortar cement bags and sand for total chamber including plaster.

1373


. Write a C program to perform following functions:- a. Declare one integer variable of all the storage classes. b. Print all the variables without assigning any values in tabular format. a. The tabular format must contain the variable name, type, storage class and printed value on the screen in RED color.

1960


Re: Can anybody help me by attaching files , formats for quality checks of common building materials like cement , concrete , bricks , sand and aggregates? please my email id is smgujjal@gmail.com

1549


Aptitude, reasoning, quants, verbal and technical question

1001


Which code specifies the specification ofthe construction joints to be provided in the raft slab of a basement which is 6 m deep.what should bethe detail of such a joint?

2044


how to calibrate the RM 800

1862