Difference between islanding and house load operation.
Answer Posted / wasim
houseload is plant's load only, whereas in islanding certain load beside plant's load is defined to feed. houseload operation usually acceptable for 1 hour
| Is This Answer Correct ? | 2 Yes | 0 No |
Post New Answer View All Answers
how to differentiate between "ALL fuel lost" and "All Fuel Lost" in Boiler MFT condition?
How do you consider that you can improve and what assistance do you need to achieve this
explain how the third harmonic content of the magnetising current affects transformer design
By any way can we increase the B check hours from 300 to 500
what is the meaning of SST300 V56A in SIEMENS turbine
can dp type level transmitter work in under vaccum condition
what is the trip circuit supervision in an electrical meaning?
im try to calculating seawater flow required for SW-FGD system. I need a guide, equation or method to do it, can some one help me! Thanks very much
why do you consider yourself a suitable candidate for this position
DCS marshaling Cabinet Power supply can be replace during plant running time? Answer Yes it is possible. I am talking about the controller and cards power supply modules. They are always redundant and connected through diode so that if one power supply fails the other can take the charge immediately.so it is possible to replace one of them in running plant if the other one is healthy. MY question is how switching done.
what is the difference between compensated & normal drum level in boiler drum?
some one can tell me how residual type excitation is provided through transformers to an AC generator without any battery or PMG&excitor
what's the moog valve
How We Calibrate the vaccum transmitter?
can u please tell me how to calculate the concrete quantity for a under reamed pile? r=300mm,depth=3m for a cylinder and for bulb l=.750mm,width=.525