How to make a Budget?
How will the user find out whether the purchases are under Budget value?
How to take out project cost report?

Answer Posted / sapmmgopal@gmail.com

Budget of Purchase Order can be routed through Internal orders.
The Process is
1. Created Project
2. Created WBS
3. Add budget to WBS and release it
4. Create Internal order and assign the WBS to it
And now you can use this Internal Order in your PO against the Item category F or K (as per your PO requirement).

User can run CJ31 with WBS element and analyse the PO/PR/Consumption against the WBS element.

There are several transactions to take the project cost.
KOB1/S_ALR_87013003 as the best.

GopalK

Is This Answer Correct ?    2 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

Explain the 'price control indicator?

690


Mention what are the data contained in the information record?

680


How to delete a batch?

687


What are the purchasing information records?

697


Can you differentiate between a sto and standard purchase order at a glance? How?

709






Which documents are used as references when we create po?

666


What is the difference between cbp and mrp?

649


If there is a pipe and you send it to a sub-contractor to be cut in to two or three pieces. How will you map such scenario in sap? Will you create separate material codes for each pipe with different length or what will be your approach?

835


What are the lot size attributes a material can posses?

718


How stock is being transferred from one plant to another plant?

659


How many stock transport orders available in sap system. And how to configure stock transport orders?

665


In bom I mentioned item category as l but when I create po for sub-contracting defaultly it shows t?

739


Why do we use document types in sap?

762


Explain control data for scheduling agreements.

1180


What are the requirements for an ‘mrp run’?

696