How to calculate the amount of Brick,cement & sand required
for 1 cum of 230mm thick brick work with ratio 1:5 please
give me an answer with detailed step
Answer Posted / suresh k
Bricks 500 no.
Cement 1.6 bags
Sand 0.3 cub-meter
| Is This Answer Correct ? | 0 Yes | 1 No |
Post New Answer View All Answers
what is mc arther pile?
what is the percentage of silt in black cotton soil.?
undistributed samples are obtained by
types of laps in column
What is progress payment?
Use of coping on terrace wall and in 4" wall is compulsory or not ?
how we can find sieve #4 is 4.75mm?
what is Brest Wall?
What is made from large rocks, which protects the base of cliffs?
do you think we shall remove un wanted soil for foundation excavation even if the thickness of the soil strata is more than 8m ?
How to calculate paint drums per meter square
I measured pcc work as 15.34 m cube , the ratio is 1:5:10 ,want to know the cement, sand and metal used for pcc measured as 15.34 m cube at this ratio.
Why should appointment store person for project ? what is the benefits for company ?
why are you joining in this (applied post) job and your aim for this job
material required for construction of 1cu.mtr wall (Cement, No of bricks (Brick size 40cm x 20cm x 10cm),sand,Quantity of water