Answer Posted / electric dood
Phasing out is a test performed on energized multi-phase circuits from different sources to ensure that like phases are connected. For example:
Red - Red
White - White
Blue - Blue
This is usually done at the point of interconnection like an isolator or bus section, ring main unit. Tools used are phasing sticks or voltmeters.
Safety precautions are always observed. Rubber gloves are worn. Phasing sticks do not physically touch the energized wires. Being in the presence of the electrical field is all that is required. Most times what is measured is phase angle. In a balanced 3-phase system each consecutive phase is spaced 120 degrees apart.
A voltmeter can be used also. The voltmeter would measure the stepped down voltages from VTs of the respective circuits. Between two phases that are in phase with the same magnitude of voltage gives a measurement of 0V.
| Is This Answer Correct ? | 6 Yes | 9 No |
Post New Answer View All Answers
1.main parts of generator? what is used A-check,B-check,C- check? 2.what is FM200 system in data centers? 3.difference between pac,ahu?
what are different types of electrical windings? i know the distributed winding ,concentrated winding etc but i want some detailed information, in what condition we will use distributed,concentrated windings what are the difference between them which is best, how induced emf changes by using different types of windings 20 hours ago - 1 week left to answer
Why wind turbines wheels rotate constantly
Why do we perform an open-circuit test and short-circuit test on the transformer?
state the working of discharge lamp?
what is photo voltic cell,& what are the materials associated with that?and any spcifications like volts/cm etc?
WHAT IS ELECTRICAL MAINTAINTENCE ?
i have 500 amp inductive load of motors ,,,pleas tell me how can i calculate for capacitor bank for improving my power factor to 99 .....calcullations for capacitor bank,,,,
A 10 MVA, 66KV, 50Hz, Y-connected 3-phase alternator has synchronous reactance of 0.635 Ù. It is working at full load at 0.8 lagging p.f. condition. Find torque angle, neglect armature resistance.
Do u know any one? how to find out in motor rated amps? formula?
Where is servomechanism used?
what is earth pit , how we can measured it, what earth rods reference
Please clarify, 1. Is it required to lay two runs of GI wire along with Armoured LT cable if it is laid between one big mains (63Amps TPN SDF) to small main (32A TPN SDF) with proper glanding termination? 2. If the armoured cable with proper glanding is laid from DB to CNC machine, is it required to run two runs of body earthing to the Machine from DB? 3.If the armoured cable with proper glanding is laid from Substation to Hangar, distance is approx. 100 mtrs, is it required to do earthing at shop area though the primary termination at substation is earthed through gland.
does buccholz in a transformer use batteries
how we design a pannel to start 10HP motor with the help of star delta starter?