how to calculate estimation for puttey... give me an example
Answer Posted / mohammed ayaz khan
As we know standard weight of wall putty= 849kg/cum
example:
vol of wall putty= area of wall putty x thickness of wall(the thickness of wall putty always 3mm i.e 0.003) take 10sq.m as example of area of wall putty
= 10x0.003
= 0.003 cu.m
standard wt of wall putty=849kg/cu.m
=standard wt of wall putty x volume of putty
= 849 x 0.003=2.54kgs And the avg of wall putty always( 5,10,20,40 kgs )
total bags = 2.54/5= 0.50 (half bag of wall putty)
1 bag of wally putty is 1200 rupees
| Is This Answer Correct ? | 0 Yes | 2 No |
Post New Answer View All Answers
To pcc 11 ft x 24 ft .How many bags of cement, sand and aggregate required? And for roofing how many cgi sheets required?
How do you convert wind speed into force?
I'm preparing to to build a simple house, but i don't know how to calculate how much cement, gravel and sand and hollow blocks i need to prepare. How many pcs of 4" or 6" hollow blocks I need for my planned 3mx6m house? thanks.
With reference to construction of state highways, please let me know the total Bill Of Quantities as per the following details:- 1) Subgrade - 500 mm 2) Granular Sub-Base (GSB) - 200 mm 3) Wet Mix Macadam I (WMM I) - 150 mm 4) Wet Mix Macadam II (WMM II) - 100 mm 5) Dense Bituminous Macadam (DBM) - 60 mm 6) Bituminous Crust (BC) - 40 mm Road Length is 44 Kms. Road Width is 7 mtrs. Please provide the BOQ of each layer as per Compacted Factor & Loose Factor both. Also, if possible please provide me the approximate details of total material required (all categories viz. soil, gravel, stone aggregrate, sand, bitumen etc.) as per general mix design prevailing in India. Thanks & Regards -- Rokr
what is the sequence of the activities in the typical under ground water tank including civil & MEP works.
Explain what is zoning permit?
What is the difference between undo & redo?
how much is the maximum compressive strength of soil cement and soil-cement-microsilica .
what is the water cement ratio of 1:6 and 1:4 cement sand mortar. reply soon
WHAT IS YOUR EXPECTED SALARY?
The building has 12 columns of 12x9 in 3 rows of 4 each in a plot of 50'x30', The central row is strengthened with 16mm twisted rods. The roof area is 1500 sft including balconies. calculate the load factor per sft. Also indicate the number of roofs the building can withstand.
a) we have 30nos., 300mm dia, 4m length double under reamed piles.calculate excavation quantity.b) tell concrete qty. also.
what will be price of 1:2:4pcc per kg?
load combinations how many types for staad design purpose?
what mean By core Billing