Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

How can step up and step down process in power transformer

Answer Posted / vinoth

Power Transformer Step UP and Step Down Process was Doing,

Basically This process depends upon No of Turns/windings of Primary and Secondary
If Step Up process,The no of turns is high in Secondary then Primary
If Step Down Process The No of turns is less in secondary then primary

Is This Answer Correct ?    1 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

Hoe do calculate the Cable size for Amps rating ?

2203


why we use four type of phase angle difference between pimary & secondry winding of a transformer & where we use them?

2143


What is the rotor frequency of 10 Hp 1440 RPM 50HZ 415V ?

1970


In which working principal temperature transmitter work.explain in detailed.

2372


How to detect voltage vector shifting in interconnection protection.

1961


How to calculate or formula to calculate rhe power in 2 phase system ??

1551


i want bhel placement paper for electrical if anybody having pl send to my id kavitha867@myway.com immediately

2029


what are the major & minor faults that occur in an inverter and in UPS ? And how to repair and resolve them ?

2402


Why we specify TNC switch with 1NO 1NC ,2NO 2NC ? how we get connection.?

1822


What is measurement?

1239


What is the form name of 'c' license, I want to download in web

1942


what about SAP/MRP regarding manufacturing of electric motors and all drives?

2064


sir pls tell me . our ct specifications are 120/5 ,2 core , 0.2 and 5p10 class , 30va and 30va buden. insted of 30 va i want use 15 va. can i use?

1556


What is the function of a neutral reactor.

1925


why it is not advisable to run low rating (19KVA) DG sets in parallel for long durations even though they are provided with droop ckts (QDC)

1958