Cemen-1
Fine agr.-2
Core agr.-3
calculate for per 100 qube feet (qubic feet wise)
Answer Posted / engr saleem mughal
Total Quantity=100 Cft
Dry Material for 100 Cft=154 Cft
Ratio=1:2:3
Sum=6
Cement=1/6*154=25.66 Cft
Sand=2/6*154=51.33 Cft
Crush=3/6*154= 77 Cft
Is This Answer Correct ? | 3 Yes | 0 No |
Post New Answer View All Answers
Curing time for 1)R.C.C slab 2)B.W 3)Plastering
Please tell me Detail cost of providing& laying nominal mix design 1:2.5:5,40mm nominal size.curing complete e/c cost of form work in foundation and plinth i/c carriage.
"Gates of the dams are generally designed of curved shape". Why?
WHAT IS THE % OF CONCRETE WASTAGES PERMITED IN A LARGE PROJECT ? AND WHICH IS CODE TO BE REFERED.
what is right & short method of measurement of slab&beam
Soil bearing capacity formula
if i used salt as a add mixture in concrete, then what will happen and what are the naturally available add mixtures.
WHERE CAN I GET THE PREVIOUS QUESTION PAPERS OF APGENCO FOR THE THE POST OF Tr.ASSISTANT ENGINEER(CIVIL)
Journal entry Gross salary 10000 Tax 1000 Employee contribution 2000 Employer contribution 2000
How reactor of SBR installed , is it be over ground, fully under ground or semi sunk ?
Coverage of 25mm.thick ratio of 1:4 cement mortar?
according to the painting co efficient, we should take the one side of doors (or) windows or both sides?
How to calculate the quantity of cement mortar 2" for mosaic tile fixing 12"x12"?
Requirement of cement, and steel 1:2:4 ratio concrete in 1128 Sqft area(Cement No of bags, steel in Kgs)
What is Density of cement, sand & aggregate ?