how to calculate the quantity of steel used for construction..
Answer Posted / rajeshkerai
Normally the steel used for the construction is calculated from the bending schedule provided with the structural drawings. if not, than it will have to be measured from the drawings. for each and every members.
Eg: If a beam of 6m long and uses 6nos 16mm reinforcement then it will be
6x6= 36m x 1.58(weight of a 16mm bar/ 1m length)= 56.80kg
if the beam is continuous than we will have to add up laps (normaly 50 x the diameter of steel).
| Is This Answer Correct ? | 11 Yes | 3 No |
Post New Answer View All Answers
Are cruise ships built for the transatlantic run?
How to calculate concret slab? W l t(4mts*5*2fts) ratio m25 grade pls tell me procedure
Which condition will prevail for the design of a swimming pool ? When the pool is empty or when it is filled ?
a) we have 30nos., 300mm dia, 4m length double under reamed piles.calculate excavation quantity.b) tell concrete qty. also.
what are the proper pipes for salt water line
if a pipe those configuration (ASTM c 76 class b 450mm dia 2500mm length) fixing for water course those lining of water is 7000 running meter. my question is that if 8 joints of pipe ls leakage and we have not permission to stop the water so which treatment we apply on joint in that in condition.
How to activate isometric axes in cad?
How to increase a bearing capacity of soil?
Does brick grows bigger every year?
i have applied 40mm spacer in the concrete for tie beam. is it correct? kindly give me if there any code available
about higyway engineering
I need model question papers for writing the Dubai municipality exam,for G+1
How about the temperature of grade 35A concrete? Does it depend on the ambient temperature?
how many spacers we need for 1 ton reinforcement? aprox.
Advantage of Aluminum form work in terms of activities can be skip and cost too