how much % of steel use in footing, slab, column
Answer Posted / sutar kalappa
the percentage of steel in different elements of structure like minimum to maximum by cross sectional area.
slab =.15 to 1%
beams= 1 to 2%
column=1% to 6%
staircase = .75%
Footing =.5% to .8%
| Is This Answer Correct ? | 23 Yes | 18 No |
Post New Answer View All Answers
Slump Values for works?
Actually i am confused that how to calculate the bending moment for a semi-circular beam and curved slab.If any one have a good idea about the matter,please give the answer with a suitable example. Thank you......
what is called the inverd level of mabhole chamber?
for 200 kg of cement how is the mix proportion in kg for m25 grade of concrete
How much quantity water should be placed in one cubic meter area?
a sewer which receives the discharge of no. of house sewer is called house sewer lateral sewer intrcepting sewer sub-main sewer
1. For 10sq.m area(47 kg bitumen contain) of 45 mm thick bitumen mix layer..how much bitumen is required for 1600 sq.m and how much aggregate need for that ?? 2. And much tonnage of bitumen mix required for 10 sq.m area of 45 mm thick. Please give answer...
What is Joule Brayton Cycle?
what is zone a n zone b?why the spacing of ring in zone a less.n zone b high?
what is the list of building construction equipment & teir output?
what is the code provision for acceptance of fineness modulus range for fine aggregates in design mix
1) a)to prepare mortar for bricklaying how much amount of water should be added for its maximum strength and workability(to avoid cracks which results, when high quantity of water is added)?is their a formula or ratio? b) suppose we want to make 1:3 mortar,what is the best way to measure cement ,sand and water and how? c)time before which freshly prepared mortar should be used? d)proper way to mix and make mortar? e)when should curing start after laying bricks and for how long?and also how many hours per day? f)what is shear wall (please in terms of layman lol) bookish definisions are confusing.... g) and last,acc to codes what are max no. of course that should be laid in a day.
If we have the center line of the Finnish road level and we want to know what level of pay would have offset the Lhs and Rhus RHS 1,2.5,5 1,2.5,5 m.
GIVE US YOUR FULL DETAIL OF THE FOLLOWING… FULL NAME.. PERMENENT MAILING ADDRESS DIRECT CONTACT NO E MAIL ADDRES.
Explain the design for rcc multi-storied building?