how do you measure the 1:2:4 and 1:1:2 proportion rcc concrete for one cubic metre? what is the cement qty. sand qty. jelly qty.
Answer Posted / tcmrs8@gmail.com
M15- 1:2:4
total value(1+2+4)= 7
if you use 40mm or 20mm aggregate, you can use ingredient value = 1.52 for 40mm, 1.56 for 20mm Aggregate.
cement 1 cum = 1440kg
= 1440/50 = 28.8 bags
so, for one cubic meter.
Cement = 1/7x1.52x28.8
= 6.25 bags
Sand = 2/7x1.52
= 0.434 cum
Agg.(40mm) = 4/7x1.52
= 0.868 cum
| Is This Answer Correct ? | 5 Yes | 2 No |
Post New Answer View All Answers
What is a bearing capacity of soil?
How to calculate volume of concrete & steel on tank foundation & ring wall ?
material used for mendrel use to bend epoxy coated rebar
what is mean by c32/40s concrete class
we have a crushing plant and our product is experiencing flakiness and elongation over limit for granite. what is the solution to this problem? how can it be avoided and what to do differently? It is not ok for batching plants
Can you pl explain the procedure steps of singly and doubly reinforced beams in limit state method
Sometimes the side of concrete bridges is observed to turn black in color. What is the reason for this phenomenon?
Why the statue of liberty is made of copper?
I have an span length 16 ft c/c
Laying bitumen concrete 40mm thick using 0.1372 cum of 13.2 10mm metal ,0.2387 cum of 10 5mm metal...what did it means please explain me how much cum of 10 mm metal need?
Bearing capacity of soil determined as per ASTM is to design the foundation size.what is the importance of EV1/EV2 value as per DIN .My consultant ask me to test the the soil as per din to find out this ratio to assess the compacted strength of soil ,,?? is it meaning full ??
how much one carpenter can doing shuttering of slab in one day
I would like to get the formula How can i calculate the productivity of a mason in terms of brick laying and plaster. i have 6000 Sqmt of interlock laying work i want to calculate - how many masons required to do the job - in how many days can it be done - what will be the production rate in 8 hours shift/ per mason if i can get some excell sheet , it will really help me in my calculations
What is geopolymer based concrete?
What is meant by autocad?