how to calculate cement bag in RCC
Answer Posted / karthik
M20 = 1:1.5:3
Volume = 1+1.5+3=5.5
Total volume ingredients for using =1.57
Volume of broken stone Require = (3/5.5) x 1.57 = 0.856 m3
Volume of sand Require = (1.5/5.5) x 1.57 = 0.471 m3
Volume of cement = (1/5.5) x 1.57 = 0.285 m3
= 0.285 x1440 = 411 kg
For 1m3 of M20 (1:1.5:3)
Broken stone = 0.856 m3
Sand = 0.472 m3
Cement = 8.22 bag
| Is This Answer Correct ? | 1 Yes | 1 No |
Post New Answer View All Answers
Can inverted beams used in pipes during construction? If yes, explain how it can be implemented?
What are the advantages of cad software?
why do we provide haunches in rcc box or underpasses?
Calculation of curtain wall of box culvert
I want to know the relevant IS codes of practice which deals with different testings of cement-sand mortar (nominal mix)that is being normally used for brick work or plaster work in the construction work.
what is anchorage length,lap length and (dont remember the last one)
Who built the sears tower?
one steel fixers how much ton steel fabrication he will do same how much tone he will binding?
Explain the water bound macadam roag
what is called Bulk Density of aggregate?
Which is the direction for positive angle?
Floor tile measurement? Wall to wall or skirting to skirting
How to get MEP technical,instaaltion & testing data for interview?
how to stop beam concrete between column
What is meant by a context menu in a cad software?