How to calculate the amount of Brick,cement & sand required
for 1 cum of 230mm thick brick work with ratio 1:5 please
give me an answer with detailed step
Answer Posted / ankush rathod
BRICK = 500
SAND = PROPORTION OF SAND IS 1:5 (1 5=6) 5/6 X 0.3=0.25CUM.
CEMENT = 1/6 X 0.3 =0.05CUM.(0.05 X 1440=72 ) 72/50=1.44
CEMENT =1.44 BAGS
| Is This Answer Correct ? | 24 Yes | 7 No |
Post New Answer View All Answers
in design case of structural member best suitrable percentage of steel limit is what
What are the phases inspections are done by local authority while construction?
How much the quantity of Dry material of Crush for 1:2:4 Concrete, using pan 3/8'' down....
How many feet are in 4 square yards?
Can we apply curing compound on ceiling (slab Bottom)
hai, kindly send anyone for output workers format details for construction project in foundation to finishing.
in staad ,why we realease a moment of a member ? what is affect if we realease a moment
Which is the indian standard code of line out. ? How much tolerance fot 1 mt lenght? Its challenge....
What is diversion tunnel in a dam?
Please design 12.5m long dubbly beam
How many lbs are there in a yard?
how to calculate number of bitumen for road asphalt
Slab quantity
How do you calculate reinforcement weight of steel?
For removal of formwork of simply supported slab / beam from where to start the deshuttering? ( Max Bending moment of the simply supported beam is in the center hence is it required to start from the supports?)