How to calculate the amount of Brick,cement & sand required
for 1 cum of 230mm thick brick work with ratio 1:5 please
give me an answer with detailed step
Answer Posted / ankush rathod
BRICK = 500
SAND = PROPORTION OF SAND IS 1:5 (1 5=6) 5/6 X 0.3=0.25CUM.
CEMENT = 1/6 X 0.3 =0.05CUM.(0.05 X 1440=72 ) 72/50=1.44
CEMENT =1.44 BAGS
| Is This Answer Correct ? | 24 Yes | 7 No |
Post New Answer View All Answers
where i can get material costs on weekly basis
Please design 12.5m long dubbly beam
What difference comes in constructing of house and a housing complex like society
What is different between DI Pipe and CI pipe?
What is the density of most of construction materials?
Whats the standard thickness of 20'/30' wide rcc service road and what will be the estimated cost per cubit feet
how to calculate the scour depth
How much is the cover for slab?
what is mean by reestimation?
What is the Null Point of chimney in Power Plant
how to calculate reinforcment in staircase cranked beam?
if mineral admixture add into concrete then what is the differences between full cement concrete & fly ash added concrete of their SP. Gr.?and for the changes of SP. Gr. what is the changes in concrete
Formula for calculating the volume of bulb in underreamed pile
in 2 way slab can additional compressive reinforcement can be provided if yes than in which conditions it is required ?
what is meant by sustainable developement as far construction field is considered. Give suitable examples to explain the same