Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

If a steel ring is 40 cm square and it's hooks are 8 dia of bar. The steel is 8mm. What is it cut length?

Answer Posted / eakub.molla

4*40+8d (where 8d indicated in the question for hook)
=160+8*.8
=166.4cm
=167cm

Is This Answer Correct ?    0 Yes 2 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

List out the potential risk factors for workers on the construction site?

1118


I need old MMUP exam question and answer for Civil engineering

1664


Define What is the distance between railway tracks?

1186


What is the software used in civil engineering?

1152


What is the outturn of Ceiling plastering

3447


For The preparation of goverment examination Which book i will prefer and by which way i will do the preparation for exam.

2179


why building got air crack? if it get in one particular are what is means?

2516


Define the various stages of the project planning process in construction.

1133


How u can calculate the Octagon ring distance from center of raft in 275 mtr chimney slipform errection? cantact no:0993455097

2324


Explain the benefits of using standard terminology in the measurement process?(Tendering and estimation)

5103


What is Critical path in Ms-Project ?

1251


What is the nature of duties & responsibilites senior civil engineer ?what is self confident & satisfaction should be a senior civil engineer?

2240


While doing civil foundation of machinery. How will you process for it? & We also fixing plates at top surface of foundation, then what is the procedure?

1234


Design a built-up column carrying an axial load of 1200 KN. Its length is 8m and it is effectively held in position at both ends and restrained against rotation at one end. Assume yield stress of 250 mpa

2275


Pls provide me with the calculation or codes related to de- shuttering of flat slabs

7013