If a steel ring is 40 cm square and it's hooks are 8 dia of bar. The steel is 8mm. What is it cut length?
Answer Posted / eakub.molla
=40*4+9*.8=160+7.2=168cm
| Is This Answer Correct ? | 0 Yes | 2 No |
Post New Answer View All Answers
can i get civil engineering test papers.......?????
Test procedure of fly ash bricks as per code ?
the volume of cement req for 70cum of brickwork in 1:6 cement mortar is approx is equal to 3cum 5cum 7cum 1ocum
For the calculation of bearing pressure below the footing, to know whether it is below the safe bearing pressure of the soil, the unit of RCC below ground level to be taken is 25 KN/m3 or (25-15)KN/m3, where 25 is the unit weight of RCC and 15 is the unit weight of soil and whether the weight of backfilling to be taken?
What is the cost of shuttering per Sqm.? How it is calculate by thumb rule...?
what is diffrence between catchment area,watershed and basin?
strength of bitumen concrete with 80-100 & 60-70 grade bitumen
what is Brest Wall?
A 16 pile group, consisting of diameter concrete piles, were cast in situ in a clayey soil whose unconfined compressive strength is 1100 psf. Each pile is 60 ft long and the pile spacing is 2.5 times the pile diameter.The water table is at the ground surface and saturated unit weight of the clay is 118 lb/cu.ft. using a factor of safety 3 and a reduction factor =0.45, compute the allowable capacity of the piles acting as individuals
i need the syllabus for the direcr recruitement of executive engineers in andhrapradesh
sir I got selected in rail vikas nigam limited and they call for interview but i don't what they will ask in interview please guide me if you have any experience
hi, i am appearing in HPCL(CIVIL ENGG.)exam. plz send me placement paper of this exam if u are having
WHAT IS THE MAIN DIFFERENCE B/W HIGHWAYS AND MOTERWAYS?
I want some common questions which have been asked in interviews of NTPC Limited,Satluj Jal Vidyut Nigam Ltd.,and Bharat Heavy Electricals Ltd.
Define line type?