form work including the props can be removed from beams only after
Answer Posted / subhayan
depends on span for upto 6m 14 days and more than that 21days
| Is This Answer Correct ? | 4 Yes | 1 No |
Post New Answer View All Answers
how much deduction will be in 32 mm dia HYSD steel bar for 45 and 90 degree bend
Can anyone tell me the sequence of the activities in a drawing room, kitchen & Toilet including civil work, finishing, electrical & plumbing fittings
what is the cost difference of a same structure when it is constructed with brick masonary and when it is constructed with block masonary and concrete as a frame structure????????????????????????
wat would be the probable interview questions and GD topics for IOCL exam?
HOW SOON CAN YOU TRAVEL DON TO ANY LOCATION POSTED U?
insted of bentonite we can use any alternate material in piling ?
What is the largest concrete dam in the world?
sir how can we find the cement and sand required for making 4" drop
Draw a neat sketch showing the 'throat' of a welding in a plate girder ?
what is the permanent solution applied for restoration of leaning tower of pisa?
what is difference between NP2 NP3 NP4 CONCRETE HUME PIPES USED AT SITE
Is there the dry coefficient of cement is constant?
How can i do RCC rate analysis?
how to estimate material requirement for an area of house in square feet?
how to preaper for interview wat they asked in interview give me idea