how to calculate cutting length in bar bending schedule for
180 degree bend? for 90 degree bend we take 2d i.e we -2d
for 180 degree ho much ? question asked at l&t
Answer Posted / tanmoy kar
It's totally a fake question bcos 180 degree bend means a straight bar . If a bar remains in straight position,then how is it possible to make a 180 degree bend.
This question was asked to verify the common sense of the candidate.
Is This Answer Correct ? | 5 Yes | 0 No |
Post New Answer View All Answers
Please let me know what is the simplest way of Calculating Mix Designs
States some of the commonly used commands in cad software’s?
What is rate for brick masonry work of 1.0 m3 in cm 1:6?
explain fie benefits of using standard terminology in the measurement process
what is differences between ferrock and concrete ?
difference between trapezoidal and pedestal footing and how the load acts on that
What is the requirement for over all CG of DG from the foundation surface to absorb the vibration of heavy set.
what is escalation?how it is done?
States some of the tool bars used in cad?
How to cal. The weight of hollow pipe?
Whats the meanig of ,'K' VALUE in the case of soil.....
What is Critical path in Ms-Project ?
How did the romans get water up hills using aqua ducts?
In earth work 1300 cum soil how to calculate how many liters require in water
What is the worlds largest concrete dam?