Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

What are the safeties in elevators?what is the use of governor in elevator?

Answer Posted / ravi

Lift safeties.
1. Hoistway Door interlock
2. Progressive Safety Gear
3. Overspeed Governor
4. Buffers
5. Limit switches
6. Overloading
7. Door Protection
8. Emergency Stop
9. Seismic Stop
10. Emergency Alarms
11. Anti Egress Locks
12.

Is This Answer Correct ?    3 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

What is order of the system?

1123


Role of active and reactive Power sharing in between two synchronized Generators, Droop Setting role ?

1755


How to use computer cpu ups use for home inverter circuit board

1783


is that a problem if i connect a single phase load to a secondry delta connected transformer but i get a neutral from other transformer i the system?

1853


what is the difference b/w UHVDC and HVDC(LIGHT)?

6743


What is the difference between shortcircuit current, rated current of cable & MCB with example? What will be the size of cable required for 5.5 KW motor (Full load current 10 Amps approx.), Starting current with DOL is 120 Amps. Aprrox. Short circuit current with LLLG fault is 2000 Amps Approx.

2042


Sir, My doubt on cable sizing calculation, Load:74 KW calculated cable 1 run 50mm2. Now client asking us to reduce cable size by increasing runs. Sir, My question now when my mind strikes with 2 options 1) Divide load 74/2 = 36 and calculate cable for 36+36 making it 2 runs or 2) Simply i can divide 50mm2 /2 ie. 2 runs of 25mm2 Please suggest me sir

1931


What is the permissable nutral current of three phase system as per IS standards?

2100


what is the function of Moulded case circuit breaker, why it is called Moulded?

1546


What are the types of power in electrical power?

1201


What are books to be referred for KPTCL exam?

3677


for a 500 KVA connected load, I calculated 30% of capactor for power correction. Even after using 225 KVR capactor PF is not improving. What could be reason for low Phase correction factor?

1957


After synchronization with grid what is the demand value QKVAR and how we will maintain that?

2256


How to calculate the sag of OPGW during stringing???

2572


Define availability (operational)?