Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

what is the weight of 8mm dia steel with 1 meter length.
Is there any formula to calculate the weight for any given
diameter

Answer Posted / sudhir kumar panwar

(3.14/4)*.008*.008*7850

steel density (7850)

answer---(.394kg/m)in tor bar

(π÷4)×d×d×steel density

Is This Answer Correct ?    0 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

if a pipe those configuration (ASTM c 76 class b 450mm dia 2500mm length) fixing for water course those lining of water is 7000 running meter. my question is that if 8 joints of pipe ls leakage and we have not permission to stop the water so which treatment we apply on joint in that in condition.

2177


where tie beam is used? what is the pupose? what dimension of tie beam can provided and number and diameter of steel bars to be used between the columns of 1333mm and 1400.

3495


what is Quantity of stone and sand required for one cubic meter of stone work (UCR)

2156


IS STEEL BARS IS AS PER ISI TRANSVERSE RIBS SHOULD BE UNIFORM IN DISTANCE, PLEASE EXPLAIN WHY,

2348


How much river sand contain the 6 & 10 wheeler truck? Or Maximum sand that any type of truck carry?

5035


what is mean by c32/40s concrete class

2017


how to prepare site mix design

2006


what is escalation?how it is done?

2572


Formula for calculating the volume of bulb in underreamed pile

5073


how to clculate the %of concrete strenght achive after curing?load

2485


How to get MEP technical,instaaltion & testing data for interview?

2260


how to remove the quantity of metal 1 and metal 2 in concrete

2029


how to calculate cost of raw materials of a building for 1000 sqft & also consolidated cost of labour in a 1000 sqft building

2910


I measured pcc work as 15.34 m cube , the ratio is 1:5:10 ,want to know the cement, sand and metal used for pcc measured as 15.34 m cube at this ratio.

2623


factory shed foundation l=4, b=3' d=8' rcc foudation for top to bottom pl tell me cement ,steel ,sand ,labour cost ,excavtion,soil is weak not so hard

2157