proportions of m10, m15, m20, m25, m30, m40, m45, m50, m60,
m70, m75, m80 etc
Answer Posted / ramveer dhakad
M5 =1:5:10
M7.5=1:4:8
M10=1:3:6
M15=1:2:4
M20=1:1.5:3
M25=1:1:2
M
| Is This Answer Correct ? | 8 Yes | 1 No |
Post New Answer View All Answers
howto calculate the quantities of material used in fly ash brick after finding the volume??
Analyze the rate for 1st class brick work in superstructure with 1:6 cement sand mortar. Consider 1000 cu.ft quantity and work out the rate per cu.ft
how many BSCs can i connect to the HUAWEI MSC
why we are useing plastic under the lean concrete?and whts the advantage?
660 square fit two story house make totally how much cement, sant, brick,aggregate, steel totally how much need
I am called for interview from north east power plant .so, I need some interview question which may help me.
foundation details for 25 ton weight Furnace on 2 supports and 2 tilters
If we buy crush sand for 3200/ Brass and cement for Rs350 /Bag and flyash 1200 / tonne....and my production is 230 Bricks per bag than how much cost is required for 1 flyash brick?
what is column foundation
How to fix the reinforcement in footing shorter bar at bottom and longer fix at top.
The portion of a brick cut across the width is called?
resins are not soluble in water soluble in spirit used in varnish left behind on evoporation of oil
what will be the total emoluments for deputy surveyor in APPSC in the payband of ( 9460-27600). please give me the detailed information step wise?
I want to know the material required per square foot in rcc roof. i.e. steel: kg/foot, cement/foot etc.
Why reinforcement done in shorter span in two way slabs