calculate 1-2-4 ration concrete - cement - sand metal and water required for 1 cum
Answer Posted / rajasekhar
C.A = 0.92
Sand = 0.46
Cement = 0.23
Cement = 0.23 × 1440 = 331.2 Kgs = 6.624 bags ~ 7 bags.
Sand = cement × 2 = 331.2 × 2 = 662.4 kgs
C.A = cement × 4 or
Sand × 2 = 662.4 × 2 = 1324.8 kgs
| Is This Answer Correct ? | 6 Yes | 1 No |
Post New Answer View All Answers
where i can get material costs on weekly basis
what is flashing?
Iwant to calculate the production of 1 labour for concrete casting which includes shuttering,scaffolding,steel fixing,concreting, deshuttering and curing in 8hours.But i am not able to determine it approximately would you pls.??
explain five benefits of using standard terminology in the measurement process?
why is M30 grade Concrete use for Foothing & Column M50
at what pressure ply-wood is obtained by gluing wooden sheets
please what are the required bars for a beams of 6mx6m and 450x300mm, one is continuous and the the second is discontinuous ..Its a commercial building (church)
std penetration resistance in very stiff clays lies bet 2 & 4 4 & 8 8 & 15 15 & 30
how much of quantity of material required for execution of one cubic meter of random rubble masonry in 1:3 cement mortar
trapozidal
what is anchorage length,lap length and (dont remember the last one)
What do you mean by bond? What are the different types of bonds?
what is w/c ratio in dry lean concrete for m10 mix design
if i used salt as a add mixture in concrete, then what will happen and what are the naturally available add mixtures.
What is M40 _ TOR - EQ and B.F.S