Answer Posted / sahilshah.civil@gmail.com
As per IS 7861 (part I) - Hot weather concreting - Temp more than 40 degree Celsius.
As per IS 7861 (part II) - Cost weather concrete - Temp below 5 degree Celsius.
Normal Temperature between 5 degree to 40 degree Celsius.
Is This Answer Correct ? | 3 Yes | 0 No |
Post New Answer View All Answers
What are the common ways of demolition?
I want some common questions which have been asked in interviews of NTPC Limited,Satluj Jal Vidyut Nigam Ltd.,and Bharat Heavy Electricals Ltd.
How many days should curing of plastering, brick work and concrete
Explain the importance of moment of inertia?
what should be the PCC ratio to construct a plinth of (40x40x4)ft...??also its estimated cost??
for 16mm thick cement plastring 1:6 on 100 Sq.m.New brick work,the quantity of cement required is.
In how many types u can do POP on ceiling and walls(on which material or by using which material)? b) what is the difference between dry , oil bound, enamel, acrlyic type of painting?
How to convert 20 dia bar to 16 dia bar in beam without reducing the steel weight
What is horizon or horizontal mining?
what is the types of surveying?which type of survey carrying for type of work?
20 mpa what is the quantity of cement sand and aggregate in one cubic meter of pcc non rainforcement concreate kindly answer including formaula thanks
cement required for construction of 400mm*200mm*200mm concrete solid blocks for 1sq.mtrs,how?
What materials were used to build the golden gate bridge?
Why reinforcement done in shorter span in two way slabs
For the symmetrical continuous beam shown in figure, Prestressed with a force P = 1500 KN along parabolic curve as shown, compute the extreme fiber stresses over the central support for the uniformly distributed load of 24 kn/m. Use load balancing method.