Calculate the quantity of concrete for the following.
2 Under-reamed cast in situ pile of 300 mm dia. of 10.00 m
length.
Answer Posted / h kumat
Volume of pile = A
= 3.14×(0.30/2)²×10=0.707m³
Volume of two undeream = B
=2× 2.44(0.30)³=0.13 m³
Totol volume of pile & underream=A+B
=0.707+0.13= 0.837m³
Be sure about shape of underream before use this formula.
| Is This Answer Correct ? | 23 Yes | 16 No |
Post New Answer View All Answers
How to plan a project
how we calculate the grade of the Bituminous materials.?????
How to do rate analysis for concrete work including shuttering work?
what is the Purpose of Adding 20% of wet mortar & 1/3rd to Dry Mortar for PCC & Plastering & Rcc .is there any standard method for adding this .?
What is the difference between absorption & adsorption and sorption?
What is the difference between 53 grade and 43 grade cement
What quantity of 1.0 m3 bricks required?
in a corner footing of a building, column lies in one corner. in this condition i want to know if the reactive pressure of soil will be uniformly distributed throughout the footing or will be uniformly varying as in the case of eccentrical loading.
For The preparation of goverment examination Which book i will prefer and by which way i will do the preparation for exam.
need to join coaching institute in coimbatore tamilnadu ......say me the best coaching for IAS
What is the difference between engineering stress and true stress?
in the construction of residential building what type of tank are used?where?why & what is its purpose?
I need to constructive work in amaraj batteries
pls give me ans to ACT formula cube testing porpuse
percentage of metal,clay or soil & water in water bond macadam roads to know the quantities for each in total volume of 11500 cubic meters