During estimation of walls of superstructure...which unit we'll use with quantity.cube or square
Answer Posted / sandeep bhardwaj
Dear student brick work measuring unit is m³ for more then half brick work,if it is less than half brick work than unit is m²
| Is This Answer Correct ? | 6 Yes | 0 No |
Post New Answer View All Answers
How much the quantity of Dry material of Crush for 1:2:4 Concrete, using pan 3/8'' down....
how to design and calculate materail quantity for concrete speedbreaker ?
which is the cheapest type of flooring (say for using for 6 months in a factory building & dismantling it)?
What are segregation and bleeding?
States some of the commonly used commands in cad software’s?
Stringer How many cm goes to landind
How to calculate Cement in bags ,sand in sqft and aggregate in sqft for 1cum M25 grade concrete
what are the types of dimensioning?
density of crush sand & crush stone or grit powder
in 100 cft = 1350 bricks in 100 cft = ? bloks
use ofr concrete as per grade ?
material used for mendrel use to bend epoxy coated rebar
How many are the types of joints?
Dear Sir What is the Contraction joint for base Slab
why demand factor less then 1 ?