During estimation of walls of superstructure...which unit we'll use with quantity.cube or square
Answer Posted / sandeep bhardwaj
Dear student brick work measuring unit is m³ for more then half brick work,if it is less than half brick work than unit is m²
| Is This Answer Correct ? | 6 Yes | 0 No |
Post New Answer View All Answers
how to calculate the weight of concrete
when reinforcement binding completed if there is more cover than the required what is the solution to reduce the cover?
How high should the water tank be to provide a 60 psi at base of this water tower?
How its coming concrete grade M 20 means 1:2:4. how it coming 1:2:4.
can you mail me detailed procedure,entire syllabus and practice papers of mpsc civil engineering branch.I am in third year now
In the design of bridge arguments what considerations should be made to select the orientation of the wing walls?
what is meant by csr in foundation? what is sbc?what is meant by contour line?
Which is the best book for building construction?
What is critical path method (c.p.m)?
what is column foundation
1.How much batten required for 1 sqm Shuttering. 2.how much pipe & clamps required for staging of 100 sqm shuttering at 5.0 m height.
How to fix the reinforcement in footing shorter bar at bottom and longer fix at top.
What is the distance between railway tracks?
how much st. steel is required for staging of concourse slab of a elevated metro station allowing through traffic .