calculate 1-2-4 ration concrete - cement - sand metal and water required for 1 cum
Answer Posted / vikas d v
For 1cum ratio is 1:2:4
Adding 40-50% for wet concrete=1.5cum
VOL=1.5/(1+2+4)=0.214cum
cement=(0.214*1*(1440/50))=6.42bags
sand= 0.214*2=0.42cum
ca=0.214*4=0.856cum
| Is This Answer Correct ? | 15 Yes | 0 No |
Post New Answer View All Answers
What is componsation
What happens to Load at yielding ?
I am a civil engineer . I am also selected for sbi clerk interview which is to be held on 4th May2010 is there anybody resembling the same? what question can be asked and what should be the probable answers?
what is cement wastage percentage in NHAI ROAD WORKS
Sometimes the side of concrete bridges is observed to turn black in color. What is the reason for this phenomenon?
Define polar co ordinates.
04. a. Slenderness ratio…………… 1 b. If the height of a stage is 15-0 & dia. of the prop is 5, the slenderness ratio is….… 1 c. If the height of a stage is 10-0 & dia of prop is 3, the number of bracing will be…… 1
Calculation of curtain wall of box culvert
How to calculate the area in squarefeets ?How much area of sqft for this measurements?East 53.3ft West 54ft North 47.7ft South 51.1ft ?
how many BSCs can i connect to the HUAWEI MSC
Define angular dimension?
What is the substitute of Mastic Asphalt?
construction workers how much time take one work or qty
how clculate excavated or backfilling quantity by simpson's rule
can we make bricks using m10 grade cement concrete and what would be the ratio of raw materials used and price per brick ?