what is the problem not getting 7 days slab cycle in Mivan
formwork? what is the output of mivan carpenter per day?
Answer Posted / er nitin lahane
Per day work for 1 carpenter is minimum 10 sqm per, I.e your shuttering area is 3250sqm you completed work in one day you are required 325 carpenter.you complete work in 8 day you required 40 carpenter per day. Ok
| Is This Answer Correct ? | 2 Yes | 0 No |
Post New Answer View All Answers
In which code the the maximum height of concrete casting has been explained
how to calculate the dry wt of sand and cement for a required design mix?for ex:M20
Civil engineering related
if i used salt as a add mixture in concrete, then what will happen and what are the naturally available add mixtures.
I want to know about rolling margin of steel :- For eg. If 2nos. bundle of 8mm dia steel with17 rods each of length 12m comes to store. During testing of 1m rod of each bundle it was found that 1rod has weight .405kg/m while other has .385kg/m. Now what will happen in case of steel payment and measurement payment ? Regards,
what is the procedure of wet seiving. n percentage of silt in different type of soil?
How do you calculate the power of a centrifugal pump?
In the different classes or grades of concrete, what is the difference between C20, M20 B20. what are the letters C, M, and B stands for.
How to build the floor to ceiling bookcase?
what is parametre for M25 after 7 days strength
what is the types of door's wood?
My daily concrete volume of M25 concrete is 1st day= 25 Cum 2nd Day = 45 Cum 3rd Day = 55 Cum 4th Day = 22 Cum 5th Day =72 Cum 7th Day = 49 Cum. What will be acceptance criteria of concrete considering as per is 456 cl.15 and table 11 (cl 16.1 and 16.3).
Special thing in designing a overhead reservoir ? which is different from an ordinary design
in plate load test what is the thickness of plate 20mm 5mm 50mm none
why we can use dust in concrete insted of fly ash