What is the difference between contingency and mitigation
plan?

Answer Posted / pk

Contingency plan: Plan the response after the risk occurs. It is post-risk
Mitigation plan: Plan to avoid or reduce the probability of risk. It is pre-risk

Is This Answer Correct ?    0 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

You know that change control systems are important as they describe how to submit change requests and document how to manage the change, track the status, and determine the management impacts of the change. Each of the following processes in the Controlling process group uses a change control system as one of its tools and techniques except: A. Integrated Change Control B. Quality Control C. Scope Change Control D. Schedule Control

601


Each of the following describes an element of the Scope Definition process except: A. Breaking down the major deliverables of the project into smaller, manageable components B. Supporting detail C. Decomposition D. Improving the accuracy of time and cost estimates

583


You are the project manager for a software consulting firm that is working on developing a new software program for a customer in another country. Things seem to be progressing well. Recently, your stakeholders examined the work of the project and formally accepted the work results. Which process was just performed? A. Scope Verification B. Quality Assurance C. Performance Reporting D. Quality Control

789


You do not expect the types of variances that have occurred on the project to date to continue. If BAC = 300, ETC = 275, PV= 300, AC = 200, EV = 250, and CPI = 1.25, what is the EAC? A. 240 B. 250 C. 475 D. 150

667


You are a project manager for Candy Works candy factory. Your project involves reporting information from the newly installed candy-counting machine to the financial system. This will give executives the ability to see production run counts at any rime during the day. The project sponsor has promised you a bonus if you get this project completed two weeks sooner than the scheduled project end date. The bonus will come in handy on your trip to the Bahamas planned for later this spring. You've got a few remaining project activities to wrap up before you can close out the project. Which of the following is the most appropriate response? A. You tell the sponsor the project is complete and treat the remaining activities as though they're problems that came up after project closure so that you can still get the bonus. B. You tell the sponsor the remaining activities are outside the scope of the project so the project really is completed and collect your bonus. C. You tell the sponsor the stakeholders added these requirements after the project was well under way and you never agreed to include them in the project so the project really is complete, and you collect your bonus. D. You tell the sponsor you aren't going to make the two-week early completion date as there are remaining activities to finish up.

684






You are preparing a cash flow analysis for a project the company is considering undertaking. The project's cost is $525,000, and expected cash inflows are $125,000 the first year and then $75,000 per quarter the second year and $100,000 per quarter after that. What is the payback period? A. 16 months B. 27 months C. 32 months D. 28 months

702


You are going to lake some performance measurements for your current project. You know that PV = 450, AC = 500, and EV= 375. What is the CPI and SPI respectively? A. CPI = .90, and SPI = 1.2. B. CPI = .75, and SPI = .83. C. CPI = 1.2, and SPI = .90. D. CPI = .83, and SPI = .75.

669


All of the following are tools and techniques of the Quality Control process except: A. Monte Carlo Analysis B. Statistical sampling C. Pareto diagrams D. Trend analysis

605


Your project was just completed. Due to some unfortunate circumstances, the project was delayed causing cost overruns at the end of the project. Which of the following is true? A. You document the circumstances as lessons learned. B. You pay particular attention to archiving the financial records for this project. C. Your project ended due to starvation because of the cost overruns. D. You document the circumstances surrounding the project completion during the Scope Verification process.

837


Ruby is an administrative assistant with another department. Her manager has agreed to loan Ruby's services to you on a part-time basis during your current project. Ruby is putting together the cost projections you've gathered so far. You want to include these costs in the project charter. Ruby is formatting this information for you into a spreadsheet package and is printing copies. Which of the following is true? A. All of the costs, including Ruby's time, are charged to the project. B. All of the costs, Ruby is typing into the spreadsheet are project costs. Ruby's time is not directly related to the project and should not be included. C. The project costs, including Ruby's time, should be included in the project charter. D. The project costs, excluding Ruby's time, should be considered project constraints.

647


What is the w5hh (wwwwwhh) principle given by barry boehm?

1179


What are the tools and techniques of the Quantitative Risk Analysis process? A. Checklists, flowcharting, interviewing B. Interviewing, sensitivity analysis, decision tree analysis, simulation C. Checklists, sensitivity analysis, decision tree analysis, information-gathering techniques D. Interviewing, checklists, assumptions analysis, risk probability impact

622


As a project manager, you're responsible for maintaining and ensuring integrity for all of the following except: A. Personal integrity of others B. Project management process C. Personal integrity D. Product integrity

691


You are a project manager in the manufacturing industry. You are using sample variance measurements to monitor the results of the process over time. Which tool and technique of Quality Control are you using? A. Statistical sampling B. Scatter diagrams C. Control charts D. Pareto diagrams

648


You are a contract project manager for a wholesale flower distribution company. Your project is to develop a website for the company that allows retailers to place their flower orders online. You will also provide a separate link for individual purchases that are ordered, packaged, and mailed to the consumer directly from the grower's site. This project involves coordinating the parent company, growers, and distributors. You are preparing a performance review and have the following measurements at hand: PV = 300; AC = 200; and EV = 250. What do you know about this project? A. The EAC is a positive number, which means the project will finish under budget. B. You do not have enough information to calculate CPI. C. The CV is a negative number in this case, which means you've spent less than what you planned as of the measurement date. D. The CV is a positive number in this case, which means you're under budget as of the measurement date.

628