How i calculate Cement sand Quantities in 100 Sq.ft Plaster?
Answer Posted / soyeb badgujar
ITS VERY SIMPLE
first we calculated total volume of plaster mortar by
area x plaster cot ( thickness of plaster )
100 inch x 0.5 inch = 50 feet cube
than check ur ratio of plaster like ( 1 : 6 )
now cement required = 1/7 x 50 = 7.14 feet cube
so cement bag = 7.14/35.28 = 0.202 meter cube
now the number of bag requirement of cement is = 0.202/.035 =5.78 approximate 6 bag requred
| Is This Answer Correct ? | 6 Yes | 3 No |
Post New Answer View All Answers
how to caluclate sienerge qty in construction in ap
why is M30 grade Concrete use for Foothing & Column M50
What is the meaning of a blue land surveyors flag?
How much 1 cum of M15, M20 & M25 concrete weigh?
rcc floor to floor 4m. in column reinforcement where we provide lap in exact location.
to minimize budget cost of building , what can i do
03. a. The water cement ratio for achieving maximum strength of concrete is…… 1 b. Water/ cement is inversely proportional to-------------- 1 c. Increasing the slump decreases the strength: True / false 1
What is the cost of shuttering per Sqm.? How it is calculate by thumb rule...?
Kindly post me previous year interview questions with answer for post of DY. Manager (civil engg.) for GAIL, NTPC, IOC, OIL and ONGC etc.
How many kilo-newtons equals 1000 kilogram?
What is the coeffiencent Friction Angle between Steel and Ashphalt?
what is idealized curve for concrere and steel
What is the difference between pvc,cpvc and upvc and where it is used as per their properties?????
List out some of the common problems that architect have to tackle it?
How to compute minimum number of columns required for a site from area of site?