what is time profile in ps?where do we define them?list the different types of time profile?
Answer Posted / harish kumar
IMG à Project System à Structures à Project Planning Board à Define-Time Profiles(OPTY) =time profile you specify the various time periods for working in the
project planning board.1 Evaluation period with the help of defines the time frame for working with and displaying
data in the project planning board. 2.Planning period with help of defines the time frame for carrying out current planning in the project planning board.
| Is This Answer Correct ? | 7 Yes | 0 No |
Post New Answer View All Answers
Is there any way by which we can stop the network from attaching further materials after it is released?
explain settlement rules
How to set field status of wbs as mandatory, (wbs element, and ntw) ?
Explain planning profile. How do you create and change it?
What is a sow?
How to set field status of wbs as mandatory, (wbs element, ntw)?
explain unit costing
What do ntw mean?
How in the project time schedule represented most often?
Can revenues be linked with activities?
Explain gnatt chart
What are the primary integration for ps?
What is the difference between validation & substitution?
How should changes controlled?
Explain value categories