what will be hook length of stirrups
Answer Posted / mukhram singh
it depends upon dia of bars...for Hook's length both side
2*10*dia.
| Is This Answer Correct ? | 4 Yes | 0 No |
Post New Answer View All Answers
As per Kandal suggestions, we have implemented rolling starts on 140 (+/- 5) degrees and we kept 3 rollars to complete the rolling before falling 125 degrees and the Aggregate AIV is below 22. But When the DBM bed is being rolled 3rd high viabration, (Before 1 plain & low ,2 high Viabrations), the aggregate is getting sharp edge agg. projections are damaged. As the literature is said that, the VG-30 Grade having better control the temp. susceptibility than Penetration grade. if so we could not get this problem at site. But we are facing on site. let me know.
what is the design procedure for building
Explain what is progress payment?
Why are pull-out tests performed for soil nails?
what is cross hair cursor?
As in practice, we are deducting every 2d for 90 degree bend but from where it comes means derivation or reference of IS Code.
what is idealized curve for concrere and steel
Explain soil analysis?
What is rate of concrete surface rendering work per sqm
In Residential home construct footing,beam, column,lintel,rcc roofs which dia rod used how to self assumed
How do you calculate reinforcement weight of steel?
What is the standard specification of MOR and Water Absorption of Homogenous Ceramic Floor Tiles?
WHAT GOAL DO YOU HAVE IN YOUR CARRIER?
i just want to know how much require sand and cement for 1 sq.mt including wastage. Please guide me as soon as possible.
I want to know the material required per Square foot in rcc roof i.e.Steel ,Cement,