Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

How to calculate the amount of Brick,cement & sand required
for 1 cum of 230mm thick brick work with ratio 1:5 please
give me an answer with detailed step

Answer Posted / md.parvez

1). Brick calculation 
take brick size =200mmx100mmx100mm
convert in meter =0.2mx.1mx.1m
total volume of brick= .2x.1x.1=0.002 cum

calculate the numbers of brick for 1cum = 1cum/0.002cum= 500 numbers of bricks.

2). cement calculation
the ratio of cement mortar =1:5
sum =1+5=6
total dry mortar requried for 1 cum brick masonary=.30cum
so, 
cement = (.30x1)/6= 0.05 cum
convert in KG=.05x1440=72KG
convert in cement bag= 72/50=1.44bag.

sand calculation
sand =(.30x5)/6=.25cum
convert in kg =.25x1440=360Kg.

Is This Answer Correct ?    248 Yes 71 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

Define What are the materials used in building a gravity dam?

1204


why top layer of block work shoud be full size if any cut block adjustable than another layer?

2149


How will you Engage Labours on Site?

1872


3. What are the disadvantages of your present job, things you do not like about it?

2773


what is density of 20mm coarse aggregate.plz send answer my below adress e.mail

2109


Which IS Code/American Code applied for coupler test of steel

2593


"Gates of the dams are generally designed of curved shape". Why?

2036


what course did you consider thinking before you enrolled in college?

2319


Explain what is alternate bid?

1243


what is the procedure involved in preparing mix design of m15 grade as per IS-10262-1982

2025


Is it necessary to apply tack coat over the primecoat. IF not what happens.answers other than 1.to superimpose the next layer(2) to adhere the layers so as to form homogenity.

1733


How its coming concrete grade M 20 means 1:2:4. how it coming 1:2:4.

1495


how many material required for brickbat water proofing of toilets.

1983


how to calclate the SHUTTERING TAKEN CONCRETE LOAD? WHAT IS THE LOAD BEARING CAPACITY IN STEEL SHUTTERING PLATE? WHAT IS THE CONCRETE LOAD IN (MASS) IN THE SHUTTERING PLATE. PLATE SIZE IS 120CM* 90CM CONCRETE WALL LENGTH IS 10M ,WIDE IS 60CM, HEIGHT IS 1.2M PLS TO SENT THE CALCULATION.

11025


WHAT IS THE MAIN DIFFERENCE B/W HIGHWAYS AND MOTERWAYS?

2418