How much cement
& coarse sand is used in 1 Sqm plaster for ratio 1:4 of  thickness 20 mm ? 

Answer Posted / piyush singh

Find the volume of the mortar by multiplying the area with the thickness in CUM unit

Volume = Area * Thickness
       = 1 sqm * (20/1000) m
       = 0.02 cum

Now increase the volume by 20% for filling of the joints

New Volume = 1.2*0.02 = 0.024 cum

Again increase the volume by 33 % for dry volume as given volume is wet volume

Dry volume = 1.33 * wet volume
           = 0.03192 cum

Now Mix proportion is 1:4 so in every 5 part of the volume 1 part is of cement and 4 part is of aggregate so 

Volume of cement = 0.03192 / 5 
                 = 0.006384

Bags of cement   = 0.006384 / 0.035
                 = 0.1824 bags
                 = 9.12 Kg

Is This Answer Correct ?    1 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

what does the track parameter mean in staad.pro?

5488


Consumption of Binding wire for fixing of cover block in vertical surface

1053


what is diffrence between catchment area,watershed and basin?

2508


I HAVE APPLIED FOR 20TH UES ARMY. I WANTED TO KNOW WHEN WILL I RECEIVE CALL LETTER FOR THE SAME.

1771


what is the cost differene of a same structure when it is constructed with brick masonary, and when it is constructed with concrete as a frame structure.????????

1486






Define aligned dimension?

676


What is kn measurement?

750


what is the proper procedure in conducting a california bearing ratio penetration test on soil on cbr machine?

1642


what is the meaning of 40/20 src

5775


How do you maintain water pressure?

665


What is critical path method (c.p.m)?

709


If we have the center line of the Finnish road level and we want to know what level of pay would have offset the Lhs and Rhus RHS 1,2.5,5 1,2.5,5 m.

1555


In foundation design, while we do the base pressure check, we normally check if the attained pressure value is less than the GROSS BEARING CAPACITY of the soil which is the sum of net bearing capacity of soil and the overburden pressure. Actually, the overburden pressure acts against the net bearing capacity of the soil and I feel that we are actually increasing the bearing capacity value and doing the check. I feel that this is NOT right. Please clarify on this.

1822


questions with answers to face an interview of an civil engineer regarding RCC buidings

2172


What is oneside mat. And explain 

2108