sir
my site not availabele 12mm steel
now if i use 10 mm how many spacing require for slab design
slab thk 200mm
footing, column,raft,wall
how can calculate
give me formula
Answer Posted / manoj
dear as you post your question is not complete.
First of all in any case as per 456:2000
The horizontal distance between parallel main
reinforcement bars shall not be more than three
times of the effective depth of solid slab or
300 mm whichever is smaller.
Let Consider 12 dia of steel @ 175 c/c
Now
A1/A2 = S1/S2
A1 is 12 dia of steel which have total cross section area 113.112 mm2 and S1 is spacing c/c is 175 mm
A2 is the steel which you want to replace have an cross section area is 77.55 mm2 and we need spacing for that.
113.112/78.55 = 175/?
and the answer is 121.52
say 122 mm c/c spacing
you can follow the same formula in any equation but with in norms.
| Is This Answer Correct ? | 3 Yes | 0 No |
Post New Answer View All Answers
Define What is the best type of wood glue?
What will be the exam pattern and syllabus for j.e post of haryana staff selection commision? Advt no. (02/2015) Some people says it would only be objective type question papers while others say it would be same as ssc (1 objective,1 conventional) ?? Please answer this question it is needfull to all.
What is the quantity of cement in mix m20 concrete?
For elevated service Reservoirs what will be the output of each skilled carpenter and bar bender.
PLS.......... ANY ONE CAN FORWARD ME PREVIOUS QUESTION PAPER hpcl civil engg
questions with answers to face an interview of an civil engineer regarding RCC buidings
Dear sir, i want to NBCC & NTPC previous exam papers email Id : madhu_bingi@yahoo.co.in
rimmer in pile foundation
How many lbs are there in a yard?
What are the main reasons for conducting pull-out tests for soil nails?
I want to know the material required per square foot in rcc roof. i.e. steel: kg/foot, cement/foot etc.
what else we can add rather than admixture in concrete to reduce the cement quantity?
What is the difference between a wood shake and wood shingles?
Can anybody help by describing each and every step in short, used while giving a building layout by total station? Regards
how to calculate the mortar for 10'*10' size room for both plastering and for masonry work?