what"s the formula find the cement consumption for brick
work 12 thick wall 1 m2?

Answer Posted / dj_mgood

It's Depend on ratio of morter.

formula is very simple.
Quantity of wet material x 1.27 = Dry morter,
Example, let suppose wet material is 100cft then
100 x 1.27 = 127cft
requied material / some of ratio
if morter is 1:4 then
1/5 * 127 = 25.4 cft
25.4/1.25 = 20.32 say 21 bags

if thickness of plaster is 1/2" then it cover 508sft Area.

Is This Answer Correct ?    1 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

What are the responsibilities of a construction manager?

792


Slump Values for works?

1765


What are your goals?

2124


Scaffolding IS code NO.

1783


by which materials we can prepare circular shuttering with tentative cost of material(rate analysis)

1698






What is the ideal size of the living room ranges from small to large size?

666


what is the minimum compressive strength of clay brick

1763


How many % we consider for lap for reinforcement for estimates

1372


Special thing in designing a overhead reservoir ? which is different from an ordinary design

765


how to take concrete quantity for precast segment for viaduct project?

2586


what is mc arther pile?

1784


What is bylayer?

686


Power grids in two adjacent states(A&B) are interconnected. Can power grid in state A can be represented by Thevenin Equivalent Circuit. If not explain Why?

1894


how much quantity of 1.5" nails and 2.5" nails are required for conventional formwork shuttering?

1224


GIVE US YOUR FULL DETAIL OF THE FOLLOWING… FULL NAME.. PERMENENT MAILING ADDRESS DIRECT CONTACT NO E MAIL ADDRES.

2046