At which place Construction joint should provide in slab
and Beam at the time of casting.
Answer Posted / alp
L/4 for Slabs and Beams
L/3 for Columns
| Is This Answer Correct ? | 0 Yes | 1 No |
Post New Answer View All Answers
what r you reqired for concrete baching plant?
What is the life of anaerobic Digester if it is used for municipal solid waste digetion.
Give me an example of a time when something you tried to accomplish and failed.
What is the difference between tor steel and tmt steel?
What is the zero value in quantity surveying
Please design 12.5m long dubbly beam
use ofr concrete as per grade ?
How do you compute moisture correction using the parameters gathered from Nuclear Density Gauge Apparatus and the moisture contents results from the lab.?
SAND AND STONE AGGREGATES WASTAGE PERCENTAGE IN CONCRETING WORK?
factory shed foundation l=4, b=3' d=8' rcc foudation for top to bottom pl tell me cement ,steel ,sand ,labour cost ,excavtion,soil is weak not so hard
3. A vane 12.5 cm long, 8.8 cm dia was pressed into a soft clay at the bottom of borehole. Torque was applied and the value at failure was 55 N-m. find the shear strength of the clay on a horizontal plane.
Explain moment of inertia and its importance.
significance of specific surface area of particles?
What is the difference between 53 grade and 43 grade cement
Concrete cover for slab, column, beam and footing?