how much nails used in 1 sq m shuttering
Answer Posted / sundarapandiyan
Shuttering qty = 6 X concrete qty
concrete qty= 0.2-0.5 X Buildup area
No of ply wood= 0.22 X shuttering area
nail in kg = 0.22 X shuttering area in sqm
oil 1 lit = 15 sqm coverage.
| Is This Answer Correct ? | 55 Yes | 2 No |
Post New Answer View All Answers
Kindly post me previous year interview questions with answer for post of DY. Manager (civil engg.) for GAIL, NTPC, IOC, OIL and ONGC etc.
primary treatment of sewagw consist of removal of floating materials removal of sand & grit removal of organic materials all above
What is quantity of cement and sand required for 2000sqft of tiling?
Why reinforcement done in shorter span in two way slabs
How to calculate concret slab? W l t(4mts*5*2fts) ratio m25 grade pls tell me procedure
how calucate cement sand ratio for plstering
how ratio is calculated for any grade of concrete. for e.g. sppose M20 requires(x;y:z) quantity of cememt sand and aggregate.
Define What is Civil Engineering?
How high should the water tank be to provide a 60 psi at base of this water tower?
Reinforced concrete: suppose you are doing rough estimate for purchase of rebar for reinforced concrete slab for single stores residential building. You know total concrete volume will be 100 m3. How many tons rebar 6, 10 and 12mm will you require for the project?
in plate load test what is the thickness of plate 20mm 5mm 50mm none
Volume of 25kg putty bag & 40 kg putty bag volume??
Can we use the flyash bricks in brick bat coba?
How much cement is require in one sqft area in a G+3 residential construction.
the magnitude of the buoyant force can be determine by newtons law of viscosity archimidies principal principles of momemnt none