you are the project manager of a project , customer is asking for a change in scope and agrees that it will be a CR. But you do not want to take the CR for whatever reason. How will you convince the customer in doing so

Answer Posted / rajeev a

Only giving the resource unavailability angle may not satisfy client, he will simply say that he is client and paying for the CR and you being a service provider should provide me what i ask...
So instead, analyse the CR completely from technical point of view along with the experts and then with delivery point of view. See what are the impacts on the existing features, quality.communicate those impacts first to the client in your client meeting..that might sound better to the client.

Is This Answer Correct ?    2 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

The project manager has the greatest influence over quality during which process? A. Quality Planning B. Quality Assurance C. Quality Control D. Quality Change Control

858


How will prioritize tasks in your projects?

548


Which logical relationship does the PDM use most often? A. Start to finish B. Start to start C. Finish to finish D. Finish to start

1022


You are a project manager for Safari Outfitters. Your company is going to offer a new product line in the upcoming spring catalog. Your project team has 10 months to secure contracts with suppliers, finalize the designs, get the product into the catalog, and stock the warehouse. This is an example of: A. An assumption because the project team has worked on projects like this before and know they can meet the 10-month deadline B. An assumption because the project team has a limited amount of time to complete the project C. A constraint because the project team has a limited amount of time to complete the project D. A constraint because the project team is working with a new product line that hasn't been developed before

605


Which organization has set the de facto standards for project management techniques? A. PMBOK B. PMO C. PMI D. PMA

1295






Change control system, configuration management, performance measurement, additional planning, and project management information system are tools and techniques of which process? A. Integrated Change Control B. Scope Change Control C. Schedule change control D. Cost change control

582


You know that change control systems are important as they describe how to submit change requests and document how to manage the change, track the status, and determine the management impacts of the change. Each of the following processes in the Controlling process group uses a change control system as one of its tools and techniques except: A. Integrated Change Control B. Quality Control C. Scope Change Control D. Schedule Control

601


What are the triple constraints? A. Time, schedules, and quality B. Time, availability, and quality C. Time, money, and schedules D. Time, money, and quality

718


You are working on a project that was proceeding well until a manufacturing glitch occurred that requires corrective action. It turns out the glitch was an unintentional enhancement to the product, and the marketing people are absolutely crazy about its potential. The corrective action is canceled, and you continue to produce the product with the newly discovered enhancement. As the project manager, you know that a change has occurred to the product scope as the glitch changed the characteristics of the product. Which of the following is true? A. Changes to product scope are reflected in the project scope. B. Changes to product scope are reflected in the integrated change control plan. C. Changes to product scope are a result of changes to the product description. D. Changes to product scope are a result of corrective action.

637


You are the project manager for Lucky Stars nightclubs. They specialize in live country and western band performances. Your newest project is in the Planning process. You are working on the WBS. The finance manager has given you a numbering system to assign to the WBS. Which of the following is true? A. The numbering system is a unique identifier known as the code of accounts, which is used to track the costs of the WBS elements. B. The numbering system is a unique identifier known as the WBS dictionary, which is used to track the descriptions of individual work elements. C. The numbering system is a unique identifier known as the code of accounts, which is used to track time and resource assignments for individual work elements. D. The numbering system is a unique identifier known as the WBS dictionary, which is used to assign quality control codes to the individual work elements. ?

591


You are the project manager for a top-secret software project for an agency of the United States Government. Your mission, should you choose to accept it, is to complete the project using internal resources. The reason is because getting top secret clearances for contractors takes quite a bit of time and waiting for clearances would jeopardize the implementation date. Your programmers are 80 percent of the way through the programming and testing work when your agency appoints a new executive director. Slowly but surely your programmers are taken off this project and reassigned to the executive director's hot new project. Which of the following type of project ending is this? A. Starvation B. Extinction C. Addition D. Integration

810


What is the key activity during Contract Closeout and Administrative Closure? A. Documenting lessons learned B. Creating project archives C. Disseminating information to formalize project closure D. Documenting project closure

634


The VP of customer service has expressed concern over a project you're involved in. His specific concern is that if the project is implemented as planned, he’ll have to purchase additional equipment to staff his customer service center. The cost is substantial and was not taken into consideration in the project budget. The project sponsor insists that the project must go forward as originally planned or the customer will suffer. Which of the following is true? A. The VP of customer service is correct. Since the cost was not taken into account at the beginning of the project, the project should not go forward as planned. Project initiation should he revisited to examine the project plan and determine how changes can be made to accommodate customer service. B. The conflict should be resolved in favor of the customer. C. The conflict should be resolved in favor of the project sponsor. D. The conflict should be resolved in favor of the VP of customer service.

688


The tools and techniques of Source Selection include all of the following except: A. Contract negotiation B. Work authorization system C. Weighting systems D. Independent estimates

786


You are a project manager for Candy Works candy factory. Your project involves reporting information from the newly installed candy-counting machine to the financial system. This will give executives the ability to see production run counts at any time during the day. You need to purchase an expensive piece of hardware as part of this project. One of the vendors bidding on the project is a close friend. In order to win the bid, she needs to know how much money the company is willing to spend on the equipment and consulting. Your friend asks you to give her this confidential information and not tell anyone you did. Which of the following is the most appropriate response? A. Tell your friend that as a PMP, you're required to abide by the Project Management Professional Code of Professional Conduct and this would violate the code as it's a conflict of interest. B. Tell your friend that as a PMP, you're required to abide by the Project Management Professional Code of Professional Conduct and this would violate the code as it’s a personal gain. C. Tell your friend that as a PMP, you're required to abide by the Project Management Professional Standards and Ethics Code and this would violate the code as it’s a conflict of interest. D. Tell your friend that as a PMP, you’re required to abide by the Project Management Professional Standards and Ethics Code and this would violate the code as it’s an ethics violation.

734